At the end of a working day, the person who did the work writes down what happened. That note is useful. It is also written from the one position most likely to carry a number that has since changed, or a problem that sounds bigger than it really is.

An internal report that is mostly right is fine. The same report sent to a client becomes something they will quote back to you. So at Balay ni Bruno & Co., before a work report turns into a client message, we re-read its checkable claims from the live system, not from the note.

What Happened on a Real Report

Two end of day notes for a client were being combined into one update to send that client. Before it went out, every claim that could be checked was checked against the live systems. That pass changed several claims, removed one problem that turned out not to exist, and found a real fault that neither note had noticed.

What the notes said

  • Contact counts written down as exact
  • A website change that "could not be rebuilt"
  • A check "proven on the real case"
  • Two records "identical down to the byte"

What the live check showed

  • Most of the counts had drifted since they were recorded
  • The finished change already existed and was live
  • The check used test records shaped like the real case, then cleared
  • The records matched in structure, which is the true claim

The new finding mattered most. One list of addresses held more people than the matching group in the contact system, so some people would have been placed into an email test they could never receive. Neither note had spotted it.

The Three Checks That Did the Most Work

1
Compare the two versions, not the page you can see

The website host keeps a list of every file in each published version. Comparing the new version with the one before it shows exactly what was added, removed and changed. That proved the homepage was untouched far better than looking at the page size, which can differ slightly from the stored file.

2
Count live, do not trust an old count

A count taken a few hours earlier was called exact. When counted again, most of the numbers had moved. Counts written down at the time of an import go out of date faster than anyone expects.

3
Test the thing a note says is impossible

The note said a page could not be rebuilt. Comparing the built file with the live page showed only the two lines that were meant to change. A stated problem is a claim like any other, and an unnecessary one costs real time and scope.

Roughly half the claims in a technical work report can be checked against the live system in a few minutes. That is a small price for not sending a client a number you later have to take back.

When to Run This Check

▲

Say which claims carry proof. Some systems only show that an automatic email sequence exists and is switched on, not the steps inside it. Anything read off a screen rather than proven from the system should be labelled that way in the report, so the reader knows what is verified and what is observed.

Why It Matters

On this report, the corrected figures included a correction the client was already owed. Sending the out of date version would have made that worse. Checking first meant the client got one accurate update instead of two corrections.

Common Questions

Why re-check a report that the person who did the work wrote?

Because a report is a memory of what happened, written by the person or tool that did the work. That is exactly where a stale number or an overstated problem is most likely to sit. Re-reading the claims from the live system before the report goes out catches those before the client sees them.

Which parts of a report should be re-checked?

Anything that can be checked: counts, statements that something was or was not changed, and any claim that something cannot be done. Counts written down earlier are the first to drift, and a claim that something is impossible is a claim like any other, so it gets tested too.

What if a claim cannot be proven from the system itself?

Say so in the report. Some tools only show that something exists and is switched on, not what happens inside it. Anything read off a screen rather than proven from the system is labelled that way, so the reader knows which claims carry proof.

Key Takeaways

  • A work report is a memory, written from the position most likely to hold an out of date number.
  • Before it reaches a client, re-check every claim you can against the live system.
  • Compare versions file by file, count live, and test anything called impossible.
  • Label what was proven and what was only seen on a screen.
  • One accurate update beats an update followed by a correction.